Back to projects

Lift Station #13 Upgrades

St. Alban's, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$73,652
Federal share40%

of $184.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of St. Alban’s
Construction start
Oct 15, 2022(actual)
Construction end
Aug 18, 2023(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 5, 2022
  • Construction end5 months lateforecast Mar 31, 2023

Also in St. Alban's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61122 in the federal list. How to read these figures.