Sanitary Sewer Treatment Plant Assessment
St. Alban's, Newfoundland and Labrador
Federal contribution
$9,975
Federal share40%
of $24.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
20222023202420252026
BuiltForecast
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of St. Albans
- Construction start
- Feb 21, 2022(actual)
- Construction end
- May 15, 2026(forecast)
Against the original forecast
- Construction start2.2 years earlyforecast May 15, 2024
Also in St. Alban's