Schedule

Announced and approvedAug 13, 2021
20222023202420252026
BuiltForecast
Program
Green Infrastructure Stream
Ultimate recipient
Town of St. Alban’s
Construction start
Feb 21, 2022(actual)
Construction end
May 15, 2026(forecast)

Against the original forecast

  • Construction start2.2 years earlyforecast May 15, 2024

Also in St. Alban's