Seal Cove Road, Water & Sewer Upgrades - Phase 3
Stephenville Crossing, Newfoundland and Labrador
Federal contribution
$362,734
Federal share40%
of $906.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
20222023
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Stephenville Crossing
- Construction start
- May 15, 2023(actual)
- Construction end
- Oct 15, 2023(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Jun 1, 2023
- Construction end7 weeks earlyforecast Nov 30, 2023