completeWastewaterGIS
Federal contribution
$599,465
Federal share40%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 28, 2024
20232024
Built

Approved 23 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Jul 5, 2023(actual)
Construction end
Oct 25, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast May 2, 2023
  • Construction end7 weeks earlyforecast Dec 15, 2023

Also in Stephenville Crossing