HVAC System Upgrades for Redevelopment of Bay St. George Public Building
Stephenville Crossing, Newfoundland and Labrador
Federal contribution
$2.8M
$2,770,737
Federal share80%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 16, 2026
202420252026
Built
Approved 2.7 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Construction start
- Jun 15, 2025(actual)
- Construction end
- Feb 26, 2026(actual)
Against the original forecast
- Construction start7 months lateforecast Oct 31, 2024
- Construction end5 weeks earlyforecast Mar 31, 2026
Also in Stephenville Crossing
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67688 in the federal list. How to read these figures.