Water and Sewer- Upgrade North Outfall

Makkovik, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$206,095
Federal share40%

of $515.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built
Program
Green Infrastructure Stream
Construction start
Jul 12, 2023(actual)
Construction end
Jul 25, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 1, 2023
  • Construction end2 months earlyforecast Sep 30, 2023

Also in Makkovik

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61160 in the federal list. How to read these figures.