Water and Sewer- Upgrade North Outfall
Makkovik, Newfoundland and Labrador
Federal contribution
$206,095
Federal share40%
of $515.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
20222023
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Inuit Community Government of Makkovik
- Construction start
- Jul 12, 2023(actual)
- Construction end
- Jul 25, 2023(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 1, 2023
- Construction end2 months earlyforecast Sep 30, 2023
Also in Makkovik