Sewer Main Replacement

Makkovik, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$483,727
Federal share40%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 16, 2026
2023202420252026
Built

Approved 3.5 years before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 11, 2024(actual)
Construction end
Jul 31, 2025(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 30, 2024
  • Construction end3 months earlyforecast Oct 31, 2025