Makkovik Spillway

Makkovik, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$271,914
Federal share50%

of $543.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Sep 1, 2018(actual)
Construction end
Oct 22, 2019(actual)

Against the original forecast

  • Construction start13 months lateforecast Jul 20, 2017
  • Construction end3 weeks lateforecast Oct 1, 2019

Also in Makkovik

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47087 in the federal list. How to read these figures.