Dam and Intake Improvements
Milltown-Head of Bay D'Espoir, Newfoundland and Labrador
Federal contribution
$181,186
Federal share40%
of $453.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 28, 2022
20222023202420252026
BuiltForecast
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Milltown-Head of Bay d'Espoir
- Construction start
- Jul 2, 2024(actual)
- Construction end
- Jul 31, 2026(forecast)
Against the original forecast
- Construction start8 weeks lateforecast May 8, 2024
Also in Milltown-Head of Bay D'Espoir