Interior Painting of Water Storage Tank

Milltown-Head of Bay D'Espoir, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$73,561
Federal share40%

of $183.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
202320242025
Built

Approved 2.5 years before the announcement.

Program
Green Infrastructure Stream
Construction start
Jul 2, 2024(actual)
Construction end
Aug 9, 2024(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2024
  • Construction end6 weeks lateforecast Jun 30, 2024