Back to projects

AVIVE Water Treatment Solution

Milltown-Head of Bay D'Espoir, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$203,358
Federal share50%

of $407.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Construction start
Nov 28, 2017(actual)
Construction end
Dec 11, 2017(actual)

Against the original forecast

  • Construction start3 months lateforecast Sep 5, 2017
  • Construction end3 weeks earlyforecast Dec 31, 2017

Also in Milltown-Head of Bay D'Espoir