Back to projects

Ville Marie Drive Street Upgrades Phases 2

Marystown, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$123,767
Federal share33%

of $371.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built
Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Marystown
Construction start
May 1, 2023(actual)
Construction end
Jun 26, 2023(actual)

Against the original forecast

  • Construction end5 months earlyforecast Nov 30, 2023

Also in Marystown