City of Dieppe - Multi-use Pathway Along Bourque Rd

Dieppe, New Brunswick

completeActive TransportationGIS
Federal contribution
$414,672
Federal share40%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 7, 2024
202220232024
Built

Approved 2.6 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Dieppe
Construction start
Sep 1, 2021(actual)
Construction end
Oct 4, 2022(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 1, 2021
  • Construction end8 weeks lateforecast Aug 12, 2022

Also in Dieppe

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61265 in the federal list. How to read these figures.