Back to projects

Acquisition of Two Electric Buses

Trois-Rivières, Quebec

completePublic TransitPTIS
Federal contribution
$1.1M
$1,082,967
Federal share40%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 17, 2023
20222023202420252026
Built

Approved 2.3 years before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
May 2, 2024(actual)
Construction end
Dec 31, 2025(actual)

Also in Trois-Rivières

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61370 in the federal list. How to read these figures.