Saint John - Retail Drive Reconfiguration
Federal contribution
$2.8M
$2,830,955
Federal share40%
of $7.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 5, 2022
today
202320242025202620272028
BuiltForecast
Approved 8 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Saint John
- Construction start
- Oct 30, 2024(actual)
- Construction end
- Mar 31, 2028(forecast)
Against the original forecast
- Construction start8 weeks lateforecast Sep 1, 2024
Also in Saint John