Fredericton Transit Upgrades
Federal contribution
$452,827
Federal share40%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2022
202220232024
Built
Approved 8 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Fredericton
- Construction start
- Jan 11, 2022(actual)
- Construction end
- Nov 30, 2023(actual)
Against the original forecast
- Construction end11 months lateforecast Dec 31, 2022
Also in Fredericton
- University of New Brunswick - Justice Building Renewal$24.9M
- Awitgati Longhouse & Cultural Centre$18.6M
- New Brunswick Broadband$16.5M
- Fredericton - Core Water and Sewer Infrastructure Multi-Year Renewal$12.6M
- Multiple Natural and Structural Infrastructure Projects to Adapt to Pluvial and Fluvial Flood Events in Fredericton$11.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61397 in the federal list. How to read these figures.