Kinkora UV Treatment Structure Upgrade
Federal contribution
$23,848
Federal share40%
of $59.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
20222023
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Community of Kinkora
- Construction start
- May 30, 2022(actual)
- Construction end
- Sep 1, 2023(actual)
Against the original forecast
- Construction start7 months lateforecast Oct 25, 2021
- Construction end4 months earlyforecast Dec 29, 2023