Fort Garry District Energy Upgrades - Ice Plant at Max Bell Centre
Federal contribution
$251,298
Federal share40%
of $628.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 17, 2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- University of Manitoba
- Construction start
- Jun 6, 2022(actual)
- Construction end
- Oct 14, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 1, 2022
- Construction end2 weeks earlyforecast Oct 31, 2022
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61519 in the federal list. How to read these figures.