THE REGIONAL TRANSIT PLAN FOR LUNENBURG COUNTY
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2024
20232024
Built
Approved 2.4 years before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Municipality of the District of Lunenburg
- Construction start
- Jul 7, 2022(actual)
- Construction end
- Apr 30, 2024(actual)
Against the original forecast
- Construction start7 months lateforecast Dec 1, 2021
- Construction end2.1 years lateforecast Mar 31, 2022
Also in Lunenburg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62129 in the federal list. How to read these figures.