Schedule

Announced and approvedAug 28, 2024
20232024
Built

Approved 2.4 years before the announcement.

Program
Permanent Public Transit Program
Construction start
Jul 7, 2022(actual)
Construction end
Apr 30, 2024(actual)

Against the original forecast

  • Construction start7 months lateforecast Dec 1, 2021
  • Construction end2.1 years lateforecast Mar 31, 2022