Prince George Kin Centre Arenas Refrigeration and Energy Recovery Upgrades
Prince George, British Columbia
Federal contribution
$1.8M
$1,778,000
Federal share40%
of $4.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 27, 2022
202320242025
Built
Approved 2 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Prince George
- Construction start
- Apr 17, 2023(actual)
- Construction end
- May 1, 2025(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Jun 1, 2023
- Construction end2 months earlyforecast Jul 1, 2025