Albert McCormick Community Centre Energy and Accessibility Retrofit

Waterloo, Ontario

underwayRecreationGICB
Federal contribution
$2.4M
$2,398,880
Federal share80%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2022
today
20222023202420252026
BuiltForecast

Approved 6 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
City of Waterloo
Construction start
Jun 2, 2025(actual)
Construction end
Aug 31, 2026(forecast)

Also in Waterloo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62312 in the federal list. How to read these figures.