Radio & Intelligent Transportation System Replacement
Federal contribution
$5.4M
$5,390,000
Federal share40%
of $13.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2022
today
2022202420262028
BuiltForecast
Approved 4 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Winnipeg
- Construction start
- Apr 1, 2023(actual)
- Construction end
- Dec 31, 2028(forecast)
Against the original forecast
- Construction start2 months earlyforecast Jun 1, 2023