Primary Transit Network Infrastructure
Federal contribution
$7.3M
$7,265,600
Federal share40%
of $18.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2022
today
202320242025202620272028
BuiltForecast
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Winnipeg
- Construction start
- Jul 1, 2024(actual)
- Construction end
- Mar 31, 2028(forecast)
Also in Winnipeg