BC Hydro - Customer Connection Project: Creative Energy Decarbonization

Vancouver, British Columbia

underwayGreen EnergyGIS
Federal contribution
$11.3M
$11,350,000
Federal share50%

of $22.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2023
2023202420252026
BuiltForecast

Approved 10 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
BC Hydro
Construction start
Feb 8, 2024(actual)
Construction end
Mar 31, 2026(forecast)

Against the original forecast

  • Construction start3 weeks earlyforecast Feb 29, 2024