Enhancing Resilience to Multiple Climate Hazards in the City of Fredericton

Fredericton, New Brunswick

underwayDisaster MitigationDMAF
Federal contribution
$8.0M
$7,984,000
Federal share40%

of $20.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 29, 2025
today
20232025202720292031
BuiltForecast

Approved 3 years before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Ultimate recipient
City of Fredericton
Construction start
Jun 1, 2022(actual)
Construction end
Dec 31, 2031(forecast)

Also in Fredericton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62533 in the federal list. How to read these figures.