Hay River and West Point First Nation – West Channel Flood Protection

Hay River, Northwest Territories

underwayDisaster MitigationDMAF
Federal contribution
$1.2M
$1,164,288
Federal share100%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 25, 2024
today
2023202420252026
BuiltForecast

Approved 16 months before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Ultimate recipient
Town of Hay River
Construction start
Jul 15, 2024(actual)
Construction end
Sep 30, 2026(forecast)

Against the original forecast

  • Construction start6 months lateforecast Jan 1, 2024

Also in Hay River

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62592 in the federal list. How to read these figures.