Stanley Avenue Business Park Watermain Rehabilitation

Niagara Falls, Ontario

completeDrinking WaterGIS
Federal contribution
$1.8M
$1,762,500
Federal share40%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
2023202420252026
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Niagara Falls
Construction start
Jul 5, 2022(actual)
Construction end
Feb 20, 2026(actual)

Against the original forecast

  • Construction end6 weeks earlyforecast Mar 31, 2026