Supervisory Control and Data Acquisition System Upgrade

Killaloe, Hagarty and Richards, Ontario

completeDrinking WaterGIS
Federal contribution
$65,000
Federal share40%

of $162.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
2022202320242025
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Jan 12, 2022(actual)
Construction end
Nov 28, 2024(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Dec 12, 2024