Back to projects

Killaloe Wastewater Pollution Control Plant Raw Sewage Grinder System replacement

Killaloe, Hagarty and Richards, Ontario

completeWastewaterCWWF
Federal contribution
$20,625
Federal share45%

of $45.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2017
20182019
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
May 23, 2018(actual)
Construction end
Dec 18, 2018(actual)

Against the original forecast

  • Construction start13 months lateforecast May 1, 2017
  • Construction end7 months lateforecast May 31, 2018

Also in Killaloe, Hagarty and Richards