Killaloe Wastewater Pollution Control Plant , Henry Street Pumping Station upgrades
Killaloe, Hagarty and Richards, Ontario
Federal contribution
$17,500
Federal share49%
of $35.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2017
20182019
Built
Approved 8 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Killaloe, Hagarty and Richards, Township of
- Construction start
- Sep 24, 2018(actual)
- Construction end
- Dec 18, 2018(actual)
Against the original forecast
- Construction start15 months lateforecast Jul 1, 2017
- Construction end7 months lateforecast May 31, 2018
Also in Killaloe, Hagarty and Richards
- Supervisory Control and Data Acquisition System Upgrade$65.0K
- Killaloe Wastewater Pollution Control Plant Raw Sewage Grinder System replacement$20.6K
- Stone Church Road and Cardinal Road Rehabilitation$19.8K
- Cameron Street Rehabilitation$14.3K
- Killaloe Wastewater Pollution Control Plant Roof Repair$10.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50248 in the federal list. How to read these figures.