Back to projects

Killaloe Wastewater Pollution Control Plant , Henry Street Pumping Station upgrades

Killaloe, Hagarty and Richards, Ontario

completeWastewaterCWWF
Federal contribution
$17,500
Federal share49%

of $35.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2017
20182019
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Sep 24, 2018(actual)
Construction end
Dec 18, 2018(actual)

Against the original forecast

  • Construction start15 months lateforecast Jul 1, 2017
  • Construction end7 months lateforecast May 31, 2018

Also in Killaloe, Hagarty and Richards

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50248 in the federal list. How to read these figures.