We Wai Kai Active Transportation Network Plan

Campbell River, British Columbia

completeCapacity BuildingATF
Federal contribution
$49,770
Federal share100%

of $49.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 20, 2022
2023
Built

Approved 6 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
We Wai Kai Nation
Construction start
Mar 31, 2023(actual)
Construction end
Oct 20, 2023(actual)

Against the original forecast

  • Construction start12 months lateforecast Apr 1, 2022
  • Construction end10 months lateforecast Dec 31, 2022