Port Hope Trails Strategy
Federal contribution
$50,000
Federal share77%
of $65.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 19, 2024
20232024
Built
Approved 21 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Municipality of Port Hope
- Construction start
- Jun 30, 2022(actual)
- Construction end
- Nov 30, 2023(actual)
Against the original forecast
- Construction start2 months earlyforecast Sep 1, 2022
- Construction end3 months lateforecast Aug 31, 2023
Also in Port Hope
- Upgrades to Port Hope Water Pollution Control Plant$4.9M
- Joint Operations Centre$1.7M
- Dorset Street Standpipe Replacement - Phase 1$1.4M
- Construction of a New Seniors/Multipurpose Community Centre as an addition at the Town Park Recreation Centre$1.2M
- Sanitary Sewer Twinning of the gravity sewer from Hope Street to the Sewage Treatment Plant to mitigate by-pass during wet weather events$772.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63215 in the federal list. How to read these figures.