Tucker House Grounds: Buildings Safety and Accessibility Upgrades
Federal contribution
$85,990
Federal share40%
of $215.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 29, 2022
202320242025
Built
Approved 3 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Tucker House Renewal Centre
- Construction start
- Apr 7, 2022(actual)
- Construction end
- Oct 30, 2025(actual)
Against the original forecast
- Construction end5 months earlyforecast Mar 31, 2026
Also in Clarence-Rockland