The reconstruction of the Centre culturel La Ronde
Federal contribution
$29,408
Federal share0%
of $6.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 3, 2024
202320242025
Built
Approved 2.6 years before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Centre Culturel La Ronde Inc.
- Construction start
- Jul 1, 2022(actual)
- Construction end
- Sep 25, 2024(actual)
Against the original forecast
- Construction end9 months lateforecast Dec 31, 2023
Also in Timmins
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63295 in the federal list. How to read these figures.