Bus Electrification Infrastructure

Waterloo, Ontario

underwayPublic TransitPTIS
Federal contribution
$1.3M
$1,320,000
Federal share40%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 26, 2024
today
2023202520272029
BuiltForecast

Approved 21 months before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
May 27, 2022(actual)
Construction end
Dec 21, 2028(forecast)

Against the original forecast

  • Construction start5 months lateforecast Jan 1, 2022