Identification, Design Features, and Prioritization of Needed Crosswalks Crossing Arterial and Collector Streets
Federal contribution
$42,940
Federal share86%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2023
20232024
Built
Approved 11 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Saint John
- Construction start
- Apr 11, 2023(actual)
- Construction end
- Jun 30, 2024(actual)
Against the original forecast
- Construction start3 months lateforecast Dec 31, 2022
- Construction end12 months lateforecast Jun 30, 2023
Also in Saint John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63460 in the federal list. How to read these figures.