Active Transportation Network Plan for the Municipality of Tache, Manitoba
Federal contribution
$50,000
Federal share95%
of $52.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 17, 2023
20232024
Built
Approved 17 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Rural Municipality of Taché
- Construction start
- Aug 2, 2023(actual)
- Construction end
- May 9, 2024(actual)
Against the original forecast
- Construction start11 months lateforecast Sep 15, 2022
- Construction end12 months lateforecast May 15, 2023