Active Transportation Plan Component of Master Transportation Plan
Prince Rupert, British Columbia
Federal contribution
$9,000
Federal share28%
of $32.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 19, 2022
2023
Built
Approved 6 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Prince Rupert
- Construction start
- May 22, 2023(actual)
- Construction end
- Jul 25, 2023(actual)
Against the original forecast
- Construction start13 months lateforecast May 2, 2022
- Construction end8 weeks lateforecast May 31, 2023
Also in Prince Rupert
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63498 in the federal list. How to read these figures.