Fox-Creek Road trail (Bell-Forêt to Melanson) and Melanson Road trail (Fox-Creek to Promenade Du Parc)
Federal contribution
$2.0M
$2,040,000
Federal share60%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 13, 2025
202320242025
Built
Approved 2.2 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Dieppe
- Construction start
- May 11, 2023(actual)
- Construction end
- Oct 23, 2025(actual)
Against the original forecast
- Construction end13 months earlyforecast Nov 30, 2026