Active Transportation Projects in Sault Ste. Marie, Ontario (2022)

Sault Ste. Marie, Ontario

underwayActive TransportationATF
Federal contribution
$841,800
Federal share60%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2023
2023202420252026
BuiltForecast

Approved 5 months before the announcement.

Program
Active Transportation Fund
Construction start
Jun 19, 2023(actual)
Construction end
Feb 1, 2026(forecast)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 1, 2023