Arbutus Greenway and W 41st Ave Crossing Project, Vancouver BC
Federal contribution
$1.7M
$1,680,000
Federal share60%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 14, 2024
20232024
The source gives no usable construction span.
Approved 15 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Vancouver
- Construction start
- Apr 12, 2024(actual)
- Construction end
- Mar 31, 2024(forecast)
Against the original forecast
- Construction start8 months lateforecast Aug 1, 2023
Also in Vancouver
- Millennium Line Broadway Extension (TransLink)$888.4M
- Vancouver Convention and Exhibition Centre Expansion$222.5M
- Seismic Upgrade and Rehabilitation of Cambie Street Bridge in Vancouver, British Columbia$84.4M
- Rapid Transit Systems Rehabilitation and Maintenance$46.2M
- Rapid Transit Fleet Expansion - SkyTrain Network$44.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63624 in the federal list. How to read these figures.