Back to projects

The Cove

Saint John, New Brunswick

approvedActive TransportationATF
Federal contribution
$813,540
Federal share60%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 16, 2024
today
20232024202520262027
BuiltForecast

Approved 13 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
City of Saint John
Construction start
May 31, 2024(forecast)
Construction end
Dec 31, 2026(forecast)