Boars Head Road Sidewalk

Saint John, New Brunswick

completeActive TransportationATF
Federal contribution
$239,078
Federal share43%

of $562.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 26, 2023
20232024
Built

Approved 6 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
City of Saint John
Construction start
May 14, 2023(actual)
Construction end
Oct 31, 2024(actual)

Against the original forecast

  • Construction end13 months lateforecast Oct 15, 2023