Active Transportation Planning in the Glebe and Central Ottawa

Ottawa, Ontario

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share100%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 14, 2023
2023
Built

Approved 17 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Glebe Community Association
Construction start
Jan 17, 2023(actual)
Construction end
Nov 30, 2023(actual)

Against the original forecast

  • Construction start5 months lateforecast Sep 1, 2022
  • Construction end9 months lateforecast Mar 1, 2023

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63725 in the federal list. How to read these figures.