Salish Sea Trail Loop: Salt Spring Segment, Southern Gulf Islands, BC
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 20, 2022
2023202420252026
Built
Approved 6 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Island Pathways
- Construction start
- Mar 31, 2022(actual)
- Construction end
- Mar 31, 2026(actual)
Against the original forecast
- Construction start3 months earlyforecast Jul 1, 2022
- Construction end7 months lateforecast Sep 1, 2025
Also in Saanich
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63727 in the federal list. How to read these figures.