Active Transportation Plan for District of Lunenburg
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 20, 2022
20232024
Built
Approved 6 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Municipality of the District of Lunenburg
- Construction start
- Jul 13, 2023(actual)
- Construction end
- Jun 25, 2024(actual)
Against the original forecast
- Construction start3 months lateforecast Mar 31, 2023
- Construction end3 months lateforecast Mar 30, 2024
Also in Bridgewater
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63735 in the federal list. How to read these figures.