Ottawa School Streets Feasibility Study
Federal contribution
$50,000
Federal share78%
of $64.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 14, 2023
20232024
Built
Approved 17 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- EnviroCentre
- Construction start
- Jul 12, 2022(actual)
- Construction end
- Feb 23, 2024(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Aug 1, 2022
- Construction end8 weeks lateforecast Dec 31, 2023