Feasibility Study & Design for the Skyline Acres Pedestrian Overpass in Fredericton, New Brunswick
Federal contribution
$50,000
Federal share50%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
2023202420252026
Built
Approved 2.6 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Fredericton
- Construction start
- Feb 27, 2024(actual)
- Construction end
- Jan 26, 2026(actual)
Against the original forecast
- Construction start14 months lateforecast Dec 31, 2022
- Construction end13 months lateforecast Dec 30, 2024
Also in Fredericton
- University of New Brunswick - Justice Building Renewal$24.9M
- Awitgati Longhouse & Cultural Centre$18.6M
- New Brunswick Broadband$16.5M
- Fredericton - Core Water and Sewer Infrastructure Multi-Year Renewal$12.6M
- Multiple Natural and Structural Infrastructure Projects to Adapt to Pluvial and Fluvial Flood Events in Fredericton$11.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63744 in the federal list. How to read these figures.