Federal contribution
$50,000
Federal share59%
of $84.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 19, 2024
20232024
Built
Approved 21 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Heart Niagara
- Construction start
- Feb 2, 2023(actual)
- Construction end
- Aug 31, 2023(actual)
Against the original forecast
- Construction start9 months lateforecast May 2, 2022
- Construction end3 months lateforecast May 31, 2023