Active Transportation Master Plan for the Region of Waterloo, Ontario
Federal contribution
$50,000
Federal share17%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 19, 2024
202320242025
Built
Approved 21 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Regional Municipality of Waterloo
- Construction start
- Jan 1, 2025(actual)
- Construction end
- May 21, 2025(actual)
Against the original forecast
- Construction start23 months lateforecast Feb 1, 2023
- Construction end4 months lateforecast Feb 1, 2025
Also in Waterloo
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63786 in the federal list. How to read these figures.